Infrastructure

The “Titanium Valley” SEZ project provides construction on the territory of the complex of the infrastructure facilities required for implementation of industrial and production activities by residents.

At present, construction of the most important off-site infrastructure facilities is in progress, preparatory works are being carried out on the site of the special economic zone, and further design and construction of engineering items is continuing .

for more details on construction
A resident of the special economic
zone will receive a plot of land
with pre-prepared engineering
infrastructure. Connection
to the service networks is free of charge.
Description Capacities/
technical
characteristics
Current
stage of
construction works
GAS SUPPLY

For gas supply to the central boiler-house, gas pipeline DN500, length 8.5 km, has been built.
On the SEZ territory, construction of a high-pressure gas line for industrial needs of resident enterprises is planned.

20 000 m3/h. Construction of the high-pressure gas line has been completed.
WATER SUPPLY

to provide water for domestic/shower/drinking needs


covering companies’ production/industrial needs, including external and internal fire-suppressing activities;


SEZ enterprises require split domestic and industrial sewerage systems with arrangement of local industrial wastewater treatment facilities, which will be located directly on the sites of the enterprises.
Treated secondary water from local industrial treatment facilities is to be used in recirculation cycles, with wastewater surpluses discharged to the stormwater drainage system.
Domestic wastewater from SEZ sites will be discharged taking into account the relief of the local system by gravity flow and pressure pipelines. Domestic and stormwater from the IPT SEZ wastewater treatment facilities will be discharged into the Melnichnaya river located to the southwest side of the SEZ site.

720 m3/day


1050 m3/day


1770 m3/day

Design works completed. Construction works started.


Construction works completed, pressure tests performed.


Design works at the completion stage

HEATING SUPPLY

For the heating supply of the first resident enterprises, the central boiler-house, capacity 7.5 MW, will be provided. At stage II, the capacity will be increased by 10 MW, with production of electric power. At stage III, the capacity of the CHP-plant will be increased by another 10 MW.
For the heating supply of the IPT SEZ site, heating networks, about 5 km long, from the CHP-plant boiler-house will be constructed. Near each site intended for location of SEZ resident enterprises, there will be a chamber for connecting resident enterprises to the heating supply.

27.5 MW Design stage
ELECTRIC POWER SUPPLY For SEZ needs, at stage 1, a 110/10 kV transformer substation, 10 MW capacity, is to be built. Later, construction of 3 more 110/10 kV substations, with capacities over 100 MW, is planned.
Also, on the SEZ site, construction of 4 power-distribution substations will be organized, which will be fed from 10/0.4 kV transformer substations to be located on residents’ sites.
120 MW Temporary electric power supply provided
Preparation works for construction of 110/10 kV transformer substation “Titanium” are being carried out
INFORMATION AND
TECHNOLOGICAL COMMUNICATION
NETWORKS
For all kinds of high-quality communications on the SEZ site, internal distribution fibre-optical networks in underground cable trays are to be provided. Communications tower has been installed, communication with the site has been provided
INTERNAL
ROAD SYSTEM
AND TRANSPORT
The internal structure of designed SEZ roads is a network of SEZ area roads, and roads on sites within resident enterprise plots. The network of internal roads has exits to external transport routes. IPT SEZ site roads are to be compulsorily sub-divided by roads for heavy trucks and for light cars.
Design specifies main (arterial) roads with relevant profiles, taking into account traffic loads, and also arrangement of required engineering services.
24 km of roads

Temporary roads to residents’ sites have been built

Construction of temporary roads with concrete-slab coatings is being carried out

Completion of design works for construction of permanent roads

RAILROAD
TRANSPORT
Inside the IPT SEZ site, an industrial railway station, sorting tracks and freight yard for receiving 20-40 foot European containers is to be provided.
The design provides the possibility for railway entrances to industrial sites, which will directly adjoin the industrial railway station, and, if necessary, the second row industrial sites.

residence map

Social infrastructure

As part of the creation of the Titanium Valley SEZ, a system of infrastructure facilities is being formed, providing complex development of the area and creating comfortable conditions for life and work for resident enterprises’ employees.

In the adjacent territories, construction of logistics facilities, social and business infrastructure, a residential area and the required social infrastructure to meet international standards is planned.